Aspreys – Foul Connection and Construction of Pelican Crossing

The foul connection in Aspreys is now complete. There remains a street light to relocate which will be undertaken between September 22nd – 24th, these works will only require a temporary footpath closure. The connection of the beacons and the lining of the zebra crossing cannot happen until notification has been made and the Traffic Regulation Order process completed.

MK Highways has received comment back from the Police and notification for the zebra crossing will commence on the 16th September 2021 for a period of 3 weeks.

Once these 3 weeks are complete the final zebra crossing works can be completed with white lining laid, beacons connected and unbagged.  These works are anticipated to be undertaken week commencing 11th October and will be carried out with temporary traffic management.

 This is a very strict formal process that needs to be followed so nothing more can happen before the notification period completes.

 Please refer to Phase 2 on the downloadable plan Section 278 Phase 1 Rollout. The plan indicates where the works will be taking place, just next to the roundabout.

We would like to apologise in advance for any disruption the works may create, the works are unavoidable but hope the community as a whole can benefit from the works once they are complete.

Should there be any concerns during the period of the works or if you need to report any urgent matters please refer to the contact details below:

M&J Evans Construction Limited – Head Office - 01543 373766

M&J Evans Construction Limited – Contracts Manager – 07929 824438

Milton Keynes Council - Out of hours Emergency Telephone – 01908 226699